Welcome to the Construction Updates page for Chippewa Intermediate School! We’re thrilled to share the latest developments on the renovation and addition project, part of our ongoing commitment to creating an enhanced learning environment for PK-6 students.

This exciting project is designed to provide improved spaces that support both student success and staff collaboration. As construction progresses, we’ll share periodic updates, so you can follow along on this transformative journey.

Week of Aug 4, 2025

  • Outside facing brick is being started on the West Wall
  • Flooring is being installed in 3 classrooms, 2 guidance offices and the teachers work room this week 8/4-8/8
  • Old girls locker room and physical education locker room is being converted into a Boys/Girls Bathroom
  • Not to worry the Team Lockeroom will be staying

Week of Aug 11, 2025

  • CIS Cafeteria has a new serving counter and the kitchen area is newly painted

Week of Aug 25, 2025

  • Walls are going up 
  • Flooring steel is in place as the addition is starting to take shape.